Blue Wave Energy Portfolio
BWC Buckmaster Pond, LLC
(DE) 30-0912550 (CSC)
Alias: Dover Landfill
Location: Powisset St., Dover, MA
Type: PV Fixed Tilt. 1 MWac / 1.42 MWdc
EPC: Conti
Constructor: Conti
Owner: AMP / Caledon JV
Topology: String Inverter
Status: Construction complete awaiting PTO from Eversource
Description
This project is built upon a closed landfill. The type of cap is earthen without membrane and the racking foundation system is ballast. Notable issue(s). Management of changes in cap thickness need to be addressed over the life of the project. Awaiting witness test and PTO.